The first H145M was rolled out, obviously with the serial 75+54, so presumably they are beginning with 75+50. So the Luftwaffe will keep their 76+.. (SOF) and Heer/Luftwaffe will ger/keep the 75+.. and 77+..(SAR).
Planned delivery for 2024 are two, 2025 four, 2026 18, 2027 21 und 2028 17. The Int. Hubschrauberausbildungszentrum will be the unit to get the first of 23 helicopters for the training role.
The first additional of five LKHs in the combat role (LUH SOF) will go to Hubschraubergeschwader 64 at the end of 2025.
Kampfhubschraubergeschwader 36 (KHRgt 36) is scheduled to receive the first helicopters in the combat role, including armament, from mid-2026.
The two Transporthubschrauberregimenter (THRgt 10 and 30) will each receive five LKHs in the training/professionalisation role from March 2027 respectively February 2028.
The 62nd and last helicopter from the firm order is scheduled to be delivered on 31 July 2028.